60 bricklayers began a 16-day project to build a castle. After five days, five of the bricklayers quit the job. If they work the same amount each day, how many extra day(s) (beyond the original estimate
asked
Feb 7, 2018
4.5k
views
1
vote
60 bricklayers began a 16-day project to build a castle. After five days, five of the bricklayers quit the job. If they work the same amount each day, how many extra day(s) (beyond the original estimate of 16) will the remaining bricklayers need?
Mathematics
college
Epic Speedy
asked
by
Epic Speedy
7.9k
points
answer
comment
share this
share
0 Comments
Please
log in
or
register
to add a comment.
Please
log in
or
register
to answer this question.
1
Answer
5
votes
The concept of answer this item is the man-days equation. This means that the man-days of the original plan should be equal to that of the real activity. From the given,
(60)(16) = (5)(60) + (11 + x)(60 - 5)
where x is the number of extra days that the bricklayers will still have to work to complete the job. The value of x from the equation is 1
Answer: 1
Lumi
answered
Feb 14, 2018
by
Lumi
8.0k
points
ask related question
comment
share this
0 Comments
Please
log in
or
register
to add a comment.
Ask a Question
Welcome to QAmmunity.org, where you can ask questions and receive answers from other members of our community.
8.6m
questions
11.3m
answers
Other Questions
How do you can you solve this problem 37 + y = 87; y =
What is .725 as a fraction
How do you estimate of 4 5/8 X 1/3
A bathtub is being filled with water. After 3 minutes 4/5 of the tub is full. Assuming the rate is constant, how much longer will it take to fill the tub?
Write words to match the expression. 24- ( 6+3)
Twitter
WhatsApp
Facebook
Reddit
LinkedIn
Email
Link Copied!
Copy
Search QAmmunity.org