117k views
2 votes
A decorator starts painting a property on 25 March. He tells the owner that if he work every day, the job will take him exactly one week. On what date can the owner expect the job to be completed?

User Ashley Lee
by
8.0k points

1 Answer

4 votes
so on April 1st because there are 31 days in March so 31-25=6, leaving 1 day in April.
User Deimos
by
7.6k points