Determined the quantity of work done when a crane lifts a 100-n block from 2m above the ground to 6 m above the ground

A100j
B200j
C400j
D600j

User Jeff Weber
by
6.6k points

1 Answer

4 votes
W=F*d=100N*(6m-2m)=400 J (C)