Earl is preparing a risk register for his organization's risk management program. which data element is least likely to be included in a risk register? description of the risk expected impact risk survey results mitigation steps

User Caltor
by
6.5k points

1 Answer

5 votes

In all of the given choices above, the element that is least likely to be included in a risk register is the risk survey results because they serve only as a basis and not considered to be an important element in which description of risk, expected impact and mitigation steps are important elements in a risk register.