If it takes 3 days for 10 workers to finish building one house, how many days will it take 15 workers to finish 4 houses?

User Adam Carr
by
7.9k points

1 Answer

2 votes
a = house
3 days x 10 worker = a
a = 30 work unit
4a = 120 work unit
120 work unit = 15 workers * y days
y = 120/15 = 8 days