103k views
0 votes
As the project progresses from initiation through planning and executing, and additional detail is gathered, the range of values for the project cost estimate will:

1 Answer

4 votes
The range of values for the project cost estimate will become more precise. As in, there will be a better and more clear idea of how much the project costs will be, so the estimate will be more accurate.
User Mily
by
6.6k points