What does "residual risk" mean in the rm process?

User Mornirch
by
6.9k points

1 Answer

2 votes
RM process stands for risk management process. The RM process includes identifying and controlling risks arising as a result of the operation.
As "residual risk" are denoted the remains of a risk and danger on which a response has been performed.
residual risk=inherent risk - impact of risk controls