If 6 men can do a piece of work in 14 days, how many men are needed to do the work in 21 days?
asked
Dec 11, 2018
104k
views
0
votes
If 6 men can do a piece of work in 14 days, how many men are needed to do the work in 21 days?
Mathematics
college
Jonno
asked
by
Jonno
7.6k
points
answer
comment
share this
share
0 Comments
Please
log in
or
register
to add a comment.
Please
log in
or
register
to answer this question.
2
Answers
6
votes
The answer should be 9 workers due to 7 day periods.
21/7 =3
3+6 =9
Answer:9
Susundberg
answered
Dec 13, 2018
by
Susundberg
7.3k
points
ask related question
comment
share this
0 Comments
Please
log in
or
register
to add a comment.
6
votes
Nine men are needed.
hope this helps
Nitesh Tarani
answered
Dec 17, 2018
by
Nitesh Tarani
8.0k
points
ask related question
comment
share this
0 Comments
Please
log in
or
register
to add a comment.
← Prev Question
Next Question →
No related questions found
Ask a Question
Welcome to QAmmunity.org, where you can ask questions and receive answers from other members of our community.
9.4m
questions
12.2m
answers
Categories
All categories
Mathematics
(3.7m)
History
(955k)
English
(903k)
Biology
(716k)
Chemistry
(440k)
Physics
(405k)
Social Studies
(564k)
Advanced Placement
(27.5k)
SAT
(19.1k)
Geography
(146k)
Health
(283k)
Arts
(107k)
Business
(468k)
Computers & Tech
(195k)
French
(33.9k)
German
(4.9k)
Spanish
(174k)
Medicine
(125k)
Law
(53.4k)
Engineering
(74.2k)
Other Questions
What is .725 as a fraction
How do you estimate of 4 5/8 X 1/3
A bathtub is being filled with water. After 3 minutes 4/5 of the tub is full. Assuming the rate is constant, how much longer will it take to fill the tub?
Twitter
WhatsApp
Facebook
Reddit
LinkedIn
Email
Link Copied!
Copy
Search Qammunity.org