117k views
0 votes
On a pert​ chart, an arrow from​ "activity d" to​ "activity e" indicates that​ _______.

1 Answer

5 votes
A project management tool used to schedule, organize and coordinate activities contained by a project is called PERT (Project Evaluation Review Technique chart). Using this chart, an arrow example from​ "activity d" to​ "activity e" is an indication that activity D must be completed before starting Activity E.



User Mateus Zitelli
by
8.5k points