Assuming that we consider the standard workday of eight hours, each part would take 18.75 minutes per part completion. In order to complete 1,250 parts, it would take 8.33 days to complete. In order to complete the 1,250 parts, the manufacturer would have to create at least eight work stations to meet the daily demand.