Answer:
4.5 days.
Explanation:
Let n represent number of days it will take Trevor to paint 3/4 of the fence.
We have been given that Trevor paints 1/6 of the fence surrounding his farm each day. So part of fence painted in n days would be
.
As Trevor needs to paint 3/4 of the fence, so we can set an equation as:






Therefore, it will take Trevor 4.5 days to paint 3/4 of the fence.