This​ year, druehl,​ inc., will produce 57 comma 60057,600 hot water heaters at its plant in​ delaware, in order to meet expected global demand. to accomplish​ this, each laborer at the plant will work 160160 hours per month. if the labor productivity at the plant is 0.150.15 hot water heaters per labor​ hour, how many laborers are employed at the​ plant?

User Wondra
by
5.8k points

1 Answer

7 votes

We know that:

rate = 0.15 heaters /labor hour

labourer time = 160 hours / month

goal = 57,600 heaters / year

We can solve this problem by simply looking at which ratios will cancel out the units:

number of labourers = (57,600 heaters/year) / [(0.15 heaters /labor hour) * (160 hours/month) * (12 month/year)

number of labourers = 200