It takes Nate five hours to paint a wall, and it takes Jill seven hours to paint the same wall. About how many hours will it will take if Nate and Jill work together to paint the wall?

User Marcv
by
7.7k points

1 Answer

3 votes
Let's use the relation:


\mathsf{(1)/(x) = (1)/(5) + (1)/(7)}\\ \\ \\ \mathsf{(1)/(x) = (7+5)/(35)}\\ \\ \\ \mathsf{(1)/(x) = (12)/(35)}\\ \\ \\ \mathsf{x = (35)/(12)}\\ \\ \\ \boxed{\mathsf{x\approx 2.92 \ h}}

It would take about 3 hours to complete the work.