Variances are calculated by subtracting the actual cost from ____

User Sebas
by
8.4k points

1 Answer

7 votes
Budgeted cost is the answer as by having the budget plan to compare to, the business, government agency, or non-profit organization can make adjustments to its management of costs or future budgets. 