if both crews work together, let's say the finish the job in "t" hours.
so.. in 1 hour, they have done 1/t of the whole work.
now, the new crew, working by itself can do the whole job in 12 hours, that means, in 1 hour, they have done only 1/12 of all the work.
the experienced crew, can do the job in 6 hours, that means in 1 hour, they have done 1/6 of all the work.
now, let's add their rates for 1 hour worth, to see what we get.

and pretty sure you know how much that is.