N operation has a 10 percent scrap rate. as a result, 72 pieces per hour are produced. what is the potential increase in labor productivity that could be achieved by eliminating the scrap

User Feinmann
by
7.6k points

1 Answer

2 votes

100% - 10% = 90%

90% = 0.90

72/0.90 = 80

they should produce 80 parts per hour which is an 8 part increase