In unit pricing, the total value of the contract is a function of the quantities needed to complete the work.

User Grahamrhay
by
7.2k points

1 Answer

4 votes
This statement is true. Unit pricing can be used in different types of contracts to require the purchaser to pay a supplier a predetermine amount per unit of product or service. The function of the quantities needed to complete the work is total value of the contract.