If 5 workers can pave 10 driveways in 30 days, how many days would it take 20 workers to pave 38 driveways?

User Smoe
by
8.5k points

1 Answer

1 vote

5*30/10 = 20x/38

150/10 = 20x/38 =

5700/200x=

x= 5700/200 = 28.5 days