If it takes 100 minutes to complete a circuit, demand at the next work center is 5 parts per minute, and a container will hold 20 parts, how many containers are required?

1 Answer

6 votes

5 parts per minute times 100 minutes = 500 parts

500/20 = 25 containers are needed