If it takes 100 minutes to complete a circuit, demand at the next work center is 5 parts per minute, and a kanban container holds 20 parts, how many containers are required?
asked
Nov 2, 2018
37.8k
views
3
votes
If it takes 100 minutes to complete a circuit, demand at the next work center is 5 parts per minute, and a kanban container holds 20 parts, how many containers are required?
Mathematics
high-school
Jon Glazer
asked
by
Jon Glazer
6.8k
points
answer
comment
share this
share
0 Comments
Please
log in
or
register
to add a comment.
Please
log in
or
register
to answer this question.
1
Answer
4
votes
5 times 100 = 500
500 divided by 20 = 25
25 containers
Gagneet
answered
Nov 8, 2018
by
Gagneet
6.0k
points
ask related question
comment
share this
0 Comments
Please
log in
or
register
to add a comment.
Ask a Question
Welcome to QAmmunity.org, where you can ask questions and receive answers from other members of our community.
8.6m
questions
11.3m
answers
Other Questions
How do you can you solve this problem 37 + y = 87; y =
What is .725 as a fraction
How do you estimate of 4 5/8 X 1/3
A bathtub is being filled with water. After 3 minutes 4/5 of the tub is full. Assuming the rate is constant, how much longer will it take to fill the tub?
i have a field 60m long and 110 wide going to be paved i ordered 660000000cm cubed of cement how thick must the cement be to cover field
Twitter
WhatsApp
Facebook
Reddit
LinkedIn
Email
Link Copied!
Copy
Search QAmmunity.org