If it takes 100 minutes to complete a circuit, demand at the next work center is 5 parts per minute, and a kanban container holds 20 parts, how many containers are required?

User Jon Glazer
by
7.2k points

1 Answer

4 votes
5 times 100 = 500
500 divided by 20 = 25
25 containers