Elijah is a warehouse production manager and has been assigned a complex project that might result in lengthy delays. in order to coordinate all aspects of the production process, elijah has created a(n _____ chart.

1 Answer

4 votes
In order to coordinate all aspects of the production process, Elijah has created a PERT chart. PERT is an acronym for Program Evaluation Review Technique. A PERT chart is a statistical project management tool which is used to organize, schedule and coordinate tasks within a project. This technique was developed in the 1950s by the USA Navy. 