To complete the 100% of (the job) washing, Roland needed 4 Hours & Sam, 3 hour,
Mind you 100% = 1
Find for each one the (job) achieved in 1 hour:
Roland achieved 1/4 & Sam 1/3 each one in 1 hour.
In one hours both will achieve 1/4+1/3 =7/12
So they will complete 7/12 (of the job) in 1 hour & for a time = t they will complete 100% (or 1) of the job, that is 1/t =7/12 & t=12/7 =1.71 hour