crew a can tunnel through a mountain in 30 days. if crew B starts from the other side at the same time, the tunnel can be completed in 18 days. how long would it take crew B working alone?

1 Answer

3 votes
39 days because 1/2 of 18 =9 and 9 plus 30 = 39