235k views
8 votes
Sheridan Company purchased land as a factory site for $1350000. Sheridan paid $114000 to tear down two buildings on the land. Salvage was sold for $8100. Legal fees of $5060 were paid for title investigation and making the purchase. Architect's fees were $47000. Title insurance cost $3500, and liability insurance during construction cost $3800. Excavation cost $15060. The contractor was paid $4500000. An assessment made by the city for pavement was $9800. Interest costs during construction were $257000.

The cost of the land that should be recorded by Wilson Co. is:______
a. $989,880
b. $980,480
c. $996,280
d. $986,880
The cost of the building should be recorded by Wilson Co. is:_______
a. 2,804,840
b. 2,813,200
c. 2,803,800
d. 3,014,240

User John Stark
by
4.9k points

1 Answer

8 votes

Answer:

a

a

Step-by-step explanation:

User Ertyui
by
5.4k points