Abby hired granite construction to build an addition onto his home. granite construction dug the foundation but then abandoned the project. granite construction is entitled to receive the full contract price minus the value of the defects.

1 Answer

1 vote
I will expect this is a valid or false question, the appropriate response is false. Abdulla is not the person who employed Granite Construction to manufacture an expansion onto his home. Rock Construction burrowed the establishment however then surrendered the venture. Stone Construction is qualified for get the full contract value short the estimation of the deformities.