165k views
2 votes
At the end of the systems implementation phase, the final report to management should include ____.

User Windix
by
8.4k points

1 Answer

0 votes
As far as I remember, at the end of the systems implementation phase, the final report to management should include these elements:

1. a comparison of actual costs and schedules to the original estimates;

2. final versions of all system documentation;

3. planned modifications and enhancements to the system that have been identified;

It's necessary thing in system analysis.

No related questions found