Number of Employees 20 Average Salary per employee $ 30,000 Weeks per year 52 Minutes available per week 2,400 Practical capacity percentage 80 % If a company uses time-driven activity-based costing, what is the practical capacity of resources supplied in minutes

1 Answer

7 votes

Answer:

1,996,800 minutes

Step-by-step explanation:

Calculation for what is the practical capacity of resources supplied in minutes

Practical capacity of resources supplied =52 weeks × 2,400 minutes per week× 80% × 20 employees

Practical capacity of resources supplied= 1,996,800 minutes

Therefore the practical capacity of resources supplied in minutes is 1,996,800 minutes