Answer: $78000
Step-by-step explanation:
First, we have to calculate the total.costnoer equivalent unit which will be the addition of the material cost per unit and the conversion cost per unit. This will be:
Material cost per unit = $220,000 / (40,000+15,000)
= $220,000 / 55000
= $4
Conversion cost per unit= $414,000 / (40,000 + (15,000*40%)
= $414000 / 46000
= $9
Therefore, total cost per equivalent unit will be: $4 + $9 = $13
Then, the equivlant unit of the ending work in process would be calculated as:
= 15,000 × 40%
= 15000 × 40/100
= 15000 × 0.4
= 6,000
The cost of the ending work in process will then be:
= 6,000 × $13
= $78,000