25.0k views
22 votes
Jenkins Company uses a job order cost system with overhead applied to jobs on the basis of direct labor hours. The direct labor rate is $20 per hour, and the predetermined overhead rate is $15 per direct labor hour. The company worked on three jobs during April. Jobs A and B were in process at the beginning of April. Job A was completed and delivered to the customer. Job B was completed during April, but not sold. Job C was started during April, but not completed. The job cost sheets revealed the following costs for April:

User Zbyszek
by
3.9k points

1 Answer

6 votes

Question Completion:

Job A Job B Job C

Cost of Jobs in Process, 4/1/2013 $12,700 $1,100 $?

Direct Materials Used 2,700 9,400 11,100

Direct Labor 11,400 9,400 3,700

Applied Manufacturing Overhead ? ? ?

Required:

If no other jobs were started, completed, or sold, determine the balance in each of the following accounts at the end of April:

A: Work In Process

B. Finished Goods

C. Cost of Goods Sold

Answer:

Jenkins Company

The balance in each of the following accounts at the end of April:

A: Work In Process = $17,575

B. Finished Goods = $26,950

C. Cost of Goods Sold = $35,350

Step-by-step explanation:

a) Data and Calculations:

Job A Job B Job C

Cost of Jobs in Process, 4/1/2013 $12,700 $1,100 $?

Direct Materials Used 2,700 9,400 11,100

Direct Labor 11,400 9,400 3,700

Applied Manufacturing Overhead 8,550 7,050 2,775

Total manufacturing costs $35,350 $26,950 $17,575

Direct labor hours 570 470 185

Direct labor rate = $20 per hour

Predetermined overhead rate = $1`5

A: Work In Process = Job C = $17,575

B. Finished Goods = Job B = $26,950

C. Cost of Goods Sold = Job A = $35,350

User ErmIg
by
3.9k points