Answer:
12 hours
Explanation:
Let t be time to fill with all pipes open
All the pipes will complete a single job that is = 1
Given is that the tank can be filled by one pipe in 4 hours and by a second pipe in 6 hours and can be drained by a third pipe in 3 hours.
So, equation forms;

=>

=>

And t = 12 hours
Hence, it will take 12 hours to do the job.