A 13 1/2 mile stretch of road needs repairs. Workers can repair 2 1/4 miles of road per week. How many weeks will it take to repair this stretch of road?
asked
May 14, 2018
216k
views
3
votes
A 13 1/2 mile stretch of road needs repairs. Workers can repair 2 1/4 miles of road per week. How many weeks will it take to repair this stretch of road?
Mathematics
middle-school
Ehsan Khaveh
asked
by
Ehsan Khaveh
6.5k
points
answer
comment
share this
share
0 Comments
Please
log in
or
register
to add a comment.
Please
log in
or
register
to answer this question.
1
Answer
4
votes
Workers can repair 4 1/2 miles of road in two weeks. Double that to get 9 miles in four weeks. Add another 4 1/2 miles in two weeks to get 13 1/2 miles. That's a total of six weeks.
You can also just multiply 9/4 by 6:
9/4x6=54/4=13.5, or 13 1/2.
Akeshwar Jha
answered
May 18, 2018
by
Akeshwar Jha
6.0k
points
ask related question
comment
share this
0 Comments
Please
log in
or
register
to add a comment.
Ask a Question
Welcome to QAmmunity.org, where you can ask questions and receive answers from other members of our community.
7.2m
questions
9.6m
answers
Other Questions
How do you estimate of 4 5/8 X 1/3
Please solve the following equation. x-6x=56
whats the most accurate estimation of 65+77
Find the additive inverse of 18/23
What is 25% of 500.00
Twitter
WhatsApp
Facebook
Reddit
LinkedIn
Email
Link Copied!
Copy
Search QAmmunity.org