218k views
5 votes
Who typically prepares the exception report?

A. The project manager
B. The project sponsor
C. Whoever on the team has the most time available
D. Whoever on the team is least likely to want to accommodate a change request

User Debasis
by
7.2k points

2 Answers

1 vote

Answer:

A

Step-by-step explanation:

User Jamiek
by
7.1k points
4 votes

Its the project manager