Joe can put up a swing set in 3 hours. Andy can put up a swing set in 5 hours. How long would it take Joe and Andy to put a swing set up if they worked together?
asked
Jan 25, 2019
211k
views
2
votes
Joe can put up a swing set in 3 hours. Andy can put up a swing set in 5 hours. How long would it take Joe and Andy to put a swing set up if they worked together?
Mathematics
college
Brandon Fosdick
asked
by
Brandon Fosdick
7.8k
points
answer
comment
share this
share
0 Comments
Please
log in
or
register
to add a comment.
Please
log in
or
register
to answer this question.
1
Answer
4
votes
Joe = 3 hours
Andy = 5 hours
If they do it together, time needed = (3 x 5) / ( 3 + 5) = 15/8 = 1 7/8 hours.
Answer: 1 7/8 hour
Darrein
answered
Jan 31, 2019
by
Darrein
7.5k
points
ask related question
comment
share this
0 Comments
Please
log in
or
register
to add a comment.
Ask a Question
Welcome to QAmmunity.org, where you can ask questions and receive answers from other members of our community.
9.0m
questions
11.6m
answers
Other Questions
What is .725 as a fraction
How do you estimate of 4 5/8 X 1/3
A bathtub is being filled with water. After 3 minutes 4/5 of the tub is full. Assuming the rate is constant, how much longer will it take to fill the tub?
i have a field 60m long and 110 wide going to be paved i ordered 660000000cm cubed of cement how thick must the cement be to cover field
Write words to match the expression. 24- ( 6+3)
Twitter
WhatsApp
Facebook
Reddit
LinkedIn
Email
Link Copied!
Copy
Search QAmmunity.org