On the assembly line it takes 2 ½ minutes to complete task one, 3 minutes 10 seconds to complete task two and 1 minute to complete the last task to make an item.How many items can be completed in 25 minutes?

User Davidselo
by
6.4k points

1 Answer

3 votes
Task 1 -----
2 (1)/(2)minutes
Task 2 ----- 3 min 10 sec = 3+10/60 =
3(1)/(6) minutes
Task 3 ----- 1 min
Total time to make 1 item =
2 (1)/(2) +
3 (1)/(6) +1 =
6 (2)/(3)minutes

In 25 minutes;

Number of items made = 25/(6 2/3) = 3.75 items = 3 items (since only a fully assembly can be regarded as an item).