A painter contractor determined the average amount of time needed to paint a house. when 2 painters are used it takes 20 hours to paint the exterior of a house. when 5 painters are used it takes 8 hours to paint the exterior of a house. let p represent the number of painters. let t represent the amount of time required to paint a house.

User Oleshko
by
7.1k points

1 Answer

3 votes

\text {2 painters take} \longrightarrow 20 \text { hours}


\text {1 painters will take} \longrightarrow 20 * 2 = 40 \text { hours}

P = number of painters.


\text {P painters will take} \longrightarrow 40 / p = (40)/(p) \text { hours}

t = total of times needed,


\boxed{\boxed {\text {Answer: }t = (40)/(p)}}