89.5k views
4 votes
One-half of a road construction project was completed by 6 workers in 12 days. working at the same rate, what is the smallest number of workers needed to finish the rest of the project in exactly four days?

1 Answer

4 votes
6 workers*12 days=x workers*4 days
x=6*12/4=3*6=18 workers are needed
User Meghs Dhameliya
by
7.7k points

No related questions found