By working 8 hours per day, Marley's team can complete a task in 15.5 days. Bill's team works on the same task at the same speed; however, Bill's team works 7 hours and 45 minutes per day. How many days
Nilesh Khisadiya
asked
Aug 11, 2023
352,121
views
26
votes
26
votes
By working 8 hours per day, Marley's team can complete a task in 15.5 days. Bill's team works on the same task at the same speed; however, Bill's team works 7 hours and 45 minutes per day. How many days does it take Bill's team to complete the task?
Mathematics
middle-school
Nilesh Khisadiya
asked
Aug 11, 2023
by
Nilesh Khisadiya
2.7k
points
answer
comment
share this
share
0 Comments
Your comment on this question:
Email me at this address if a comment is added after mine:
Email me if a comment is added after mine
Privacy: Your email address will only be used for sending these notifications.
Add comment
Cancel
Your answer
Email me at this address if my answer is selected or commented on:
Email me if my answer is selected or commented on
Privacy: Your email address will only be used for sending these notifications.
Add answer
Cancel
2
Answers
17
votes
17
votes
The ratio of numbers of days required is the reciprocal of the ratio of the number of hours worked per day. Think of examples with easier numbers: if you work on a project 4 hours a day, it will take you 2 times as long as if you work 8 hours a day.
ratio of hours worked per day: 7 3/4 to 8 = 31 to 32
ratio of number of days required: 32:31
number of days required by Bill's team: 15.5%2A%2832%2F31%29+=+%2831%2F2%29%2A%2832%2F31%29+=+32%2F2+=+16
Ben Green
answered
Aug 12, 2023
by
Ben Green
3.1k
points
ask related question
comment
share this
0 Comments
Your comment on this answer:
Email me at this address if a comment is added after mine:
Email me if a comment is added after mine
Privacy: Your email address will only be used for sending these notifications.
Add comment
Cancel
23
votes
23
votes
It will take 16 days.
8 Hours x 15.5 days = 124 Hours
Using this logic, we know 60 minutes in an hour and 45/60= .75. So it is 7.75 Hours.
124/7.75= 16.
Hope this helps :)
Ted Johnson
answered
Aug 15, 2023
by
Ted Johnson
3.2k
points
ask related question
comment
share this
0 Comments
Your comment on this answer:
Email me at this address if a comment is added after mine:
Email me if a comment is added after mine
Privacy: Your email address will only be used for sending these notifications.
Add comment
Cancel
Ask a Question
Welcome to QAmmunity.org, where you can ask questions and receive answers from other members of our community.
1.6m
questions
2.0m
answers
Other Questions
Evalute 8a -1+0.5b when a =1/4 and b= 10 how dose this work i need help..
PLZ needed now plz URGENT!
Yall help me out please
Alguien que hable ESPAÑOL :)