6.4k views
3 votes
Two constructors working together finished building a room in 6 days. how long would it take for each constructor to build the room by himself, if it is known that one of them would require 9 more days than the other?

2 Answers

2 votes
It would take one construction worker 9 days and the other 18 days.

Let x be the number of days the first construction worker takes to build the room by himself. If x were 2, he could build 1/2 of the room in the time limit, etc...so 1/x will be the portion of the room he can build by himself in the given tie limit.

The second construction worker can build 1/(x+9) of the room by himself in the given time limit.

Together, we have the equation
1/x(6) + 1/(x+9)(6) = 1

[The speed of the first contractor times the number of days, and the speed of the second contractor times the number of days; together they build 100% of the room]

This gives us

6/x+ 6/(x+9) = 1

We will multiply everything by x to get it off of the denominator:
6/x(x) +(6/(x+9))(x)= x
6 + 6x/(x+9) = x

Multiply everything by x+9 now:

6(x+9) + (6x/(x+9))(x+9) = x(x+9)
6x + 54 + 6x = x² + 9x
12x + 54 = x² + 9x

Subtract 12x from each side:
12x + 54 - 12x = x²+9x-12x
54 = x²-3x

Subtract 54 from each side:
54-54 = x²-3x-54
0 = x²-3x-54

This factors easily; -9(6) = -54 and -9+6 = -3:
0 = (x-9)(x+6)

Using the zero product property we know either x-9=0 or x+6=0; this gives us x=9 or x=-6. Negative time makes no senses, so x=9 hours.

This means the slower contractor takes 9+9 = 18 hours.
User Maxbc
by
8.6k points
4 votes

Answer:

It would take 10 days to the first constructor and 15 days to the second one to finish the room.

Explanation:

Time to finish the room with both constructors: 6 days.

Time to finish the room by the first constructor only: x days.

Time to finish the room by the second constructor only: (x + 5) days.

If we associate all that, 1 day work of both constructors working at the same time would be
(1)/(6)

1 day work of the first is:
(1)/(x)

1 day work of the second is:
(1)/(x+5)

Now, we need to find the variable, using the following equation


(1)/(x)+(1)/(x+5)=(1)/(6)\\(x+5+x)/(x^(2) +5x) =(1)/(6)\\12x+30=x^(2) +5x\\ x^(2) +5x-12x-30=0\\ x^(2) -7x-30=0

Then, we need to find two numbers which product is 30, and which difference is 7. Those numbers are 10 and 3, because 10 times 3 is 30, and 10 minus 3 is 7.


x^(2) -7x-30=(x-10)(x+3)=0

Using the zero factor property, we have


x-10=0 \implies x=10\\x+3=0 \implies x=-3

But, only the positive number makes sense. Replacing the value in each expression we have

First constructor:
x=10 days.

Second constructor:
x+5=10+5=15 days,

Threfore, it would take 10 days to the first constructor and 15 days to the second one to finish the room.

User Martinus
by
8.8k points
Welcome to QAmmunity.org, where you can ask questions and receive answers from other members of our community.