Cpm/pert graphically displays the scheduling of tasks required to complete a project. a. True b. False
asked
Apr 19, 2019
69.5k
views
4
votes
Cpm/pert graphically displays the scheduling of tasks required to complete a project.
a. True
b. False
Mathematics
college
Jeanny
asked
by
Jeanny
6.2k
points
answer
comment
share this
share
0 Comments
Please
log in
or
register
to add a comment.
Please
log in
or
register
to answer this question.
1
Answer
4
votes
a is the answer for this question
DragonBobZ
answered
Apr 25, 2019
by
DragonBobZ
6.4k
points
ask related question
comment
share this
0 Comments
Please
log in
or
register
to add a comment.
Ask a Question
Welcome to QAmmunity.org, where you can ask questions and receive answers from other members of our community.
6.4m
questions
8.5m
answers
Other Questions
What is the least common denominator of the four fractions 20 7/10 20 3/4 18 9/10 20 18/25
What is 0.12 expressed as a fraction in simplest form
Solve using square root or factoring method plz help!!!!.....must click on pic to see the whole problem
What is distributive property ?
What is the measure of xyz
Twitter
WhatsApp
Facebook
Reddit
LinkedIn
Email
Link Copied!
Copy
Search QAmmunity.org