The first group was responsible for making 160 suits while the second group was responsible for making 25% fewer suits in the same amount of time. The first team made 10 more suits each day than the second team and finished its job 2 days before the deadline date. How many suits did the second team make each day if it needed two days extra after the deadline to finish the assigned job?

User Sandover
by
6.1k points

1 Answer

5 votes
First group rate is x+10, Second is x
First group made 160, Second made 120
Time the first group will take is 160/x+10, and second is 120/x
Equation is: 160/x+10 + 4 = 120/x
x=10, x=-30
The second group made 10 suits everyday.