37.7k views
1 vote
A new sidewalk will be 4 ft wide, 280 ft long, and filled to a depth of 9 inches (0.75 ft) with concrete. How many cubic yards of concrete are needed?

User BlueSurfer
by
8.3k points

1 Answer

4 votes

Answer:

Volume of the pit is
31.11 cubic yards.

Explanation:

First lets change all the values to yards.

1 yard = 3 foot

Width in yards =
(4)/(3) yards

Length in yards =
(280)/(3) yards

Depth in yards =
(0.75)/(3) yards


Volume of the pit = Length * Width * Depth

=
(4)/(3) *(280)/(3) *(0.75)/(3)

=
(4*280*0.75)/(3*3*3)

=
(840)/(27)

=
31.11 cubic yards.

Volume of the pit is
31.11 cubic yards.

User Gines
by
8.6k points