There may be more than one critical path in a project network.

b. if one of the activities on the critical path is​ delayed, the entire project will be delayed.
c. the critical path is the sequence of activities between a​ project's start and finish that takes the shortest time to complete.
d. the activities along the critical path determine the completion time of the project.

User Amer
by
6.7k points

1 Answer

2 votes
The answer is c, the critical path is the sequence of activities between a projects start and finish that takes the shortest time to complete.