A mining company owns two mines. These mines produce an ore that can be graded into two classes: regular grade and low grade. The c

at least 380 tons of regular-grade and 610 tons of low-grade ore per week. The first mine produces 6 tons of regular-grade and 17 tons o
hour. The second mine produces 20 tons of regular-grade and 10 tons of low-grade ore per hour. The operating cost of the first mine is $
operating cost of the second mine is $28,000 per hour. The first mine can be operated no more than 40 hours a week, and the second ml
more than 27 hours a week. How many hours per week should each mine be operated to minimize the cost?
Note that the ALEKS graphing calculator can be used to make computations easier.
Answer :
first mine : 40 hour(s)
Second mine : 7 hour(s)

User Xiaoboa
by
3.3k points

1 Answer

18 votes
18 votes
380 cause In the passage it says