Your crew can pave two driveways in a day. You work five days per week but take off 2 weeks each year for holidays and vacations. How many driveways could your crew pave in a year?
asked
Jun 12, 2019
139k
views
4
votes
Your crew can pave two driveways in a day. You work five days per week but take off 2 weeks each year for holidays and vacations. How many driveways could your crew pave in a year?
Mathematics
high-school
Vireshas
asked
by
Vireshas
6.3k
points
answer
comment
share this
share
0 Comments
Please
log in
or
register
to add a comment.
Please
log in
or
register
to answer this question.
1
Answer
5
votes
500.
2 a day times five days a week, times 50 weeks, (each year is 52 weeks, take two off) this equals 500.
Fenio
answered
Jun 18, 2019
by
Fenio
7.1k
points
ask related question
comment
share this
0 Comments
Please
log in
or
register
to add a comment.
Ask a Question
Welcome to QAmmunity.org, where you can ask questions and receive answers from other members of our community.
7.2m
questions
9.5m
answers
Other Questions
How do you estimate of 4 5/8 X 1/3
Please solve the following equation. x-6x=56
whats the most accurate estimation of 65+77
Find the additive inverse of 18/23
What is 25% of 500.00
Twitter
WhatsApp
Facebook
Reddit
LinkedIn
Email
Link Copied!
Copy
Search QAmmunity.org