73.8k views
4 votes
Operation x feeds into operation y. operation x has an effective capacity of 55 units per hour. operation y has an effective capacity of 50 units per hour. increasing x's effective capacity to ensure that y's utilization is maximized would be an example of ________ a constraint.

1 Answer

6 votes

Theory of Constraints



User FireZenk
by
8.1k points

No related questions found

Welcome to QAmmunity.org, where you can ask questions and receive answers from other members of our community.