A factory needs to produce 1,800 jars of peanut butter on a certain day.

They start production at 8:30 A.M. By 10:30 A.M., they have produced 600 jars of peanut butter.
At what time will they complete the total number of jars that they need to produce?
A. 12:30 P.M.
B. 1:30 P.M.
C. 2:30 P.M.
D. 3:30 P.M.

1 Answer

9 votes

Answer:

d

Explanation:

because in 2 they make 600 and 600 times 3 is 1,800 then do 2 times 3 witch is 6 so 6 hours after 10:30 is 3:30. I hope that makes sense <3