You work as a coordinator for data entry projects. On one project, the status report shows that 15% of the work was completed in 6 days. If the work progresses at the same rate, how many more days will be required to complete the remainder of the project?

2 Answers

0 votes

Answer: They need 34 more days to complete the remainder of the project.

Explanation:

Since we have given that

Number of days the work was done = 6 days

Part of work is completed in these days = 15%

If the work is done at the same rate,

then the remaining part of work is done in how many days.

Remaining part of work is 100% - 15% = 85 %

So, it becomes,


(6)/(0.15)=(x)/(0.85)\\\\x=(6* 0.85)/(0.15)=34\ days

Hence, they need 34 more days to complete the remainder of the project.

User George Marques
by
7.6k points
4 votes
The remaining 85% will take 85/15 * 6 days = 34 days to complete.
User Bravo Net
by
8.3k points

No related questions found

Welcome to QAmmunity.org, where you can ask questions and receive answers from other members of our community.

9.4m questions

12.2m answers

Categories