Contractor A estimated a job would cost $54,000 to complete in 90 days.
Per day charge of Contractor A = $54,000 / 90 = $ 600 / day
Contractor B estimated he could complete the same job for $49,500 in 120 days.
Per day charge of Contractor A = $49,500 / 90 = $ 412.50 / day
Therefore, Contractor A charges $ 600 per day and contractor B charges $412.50 per day.