Solve the problem as directed. The time it takes to lay a sidewalk of a certain type varies directly as the length and inversely as the number of men working. If eight men take two days to lay 100 feet,
asked
Dec 28, 2019
164k
views
5
votes
Solve the problem as directed. The time it takes to lay a sidewalk of a certain type varies directly as the length and inversely as the number of men working. If eight men take two days to lay 100 feet, how long will three men take to lay 150 feet?
Mathematics
middle-school
Sidi Shah
asked
by
Sidi Shah
7.2k
points
answer
comment
share this
share
0 Comments
Please
log in
or
register
to add a comment.
Please
log in
or
register
to answer this question.
2
Answers
3
votes
150/18.75=18.75 feet per day
150/18.75=17.14 days
Afrad Ahsan
answered
Dec 31, 2019
by
Afrad Ahsan
8.3k
points
ask related question
comment
share this
0 Comments
Please
log in
or
register
to add a comment.
3
votes
T = k L / N where k is the constant of variation
2 = k * 100 / 8
100k = 16
k = 0.16
so fromula is
T = 0.16L / N
when L = 150 and N = 3 we have
Time taken T = 016* 150 / 3 = 8 days answer
Cristian Curti
answered
Jan 4, 2020
by
Cristian Curti
9.2k
points
ask related question
comment
share this
0 Comments
Please
log in
or
register
to add a comment.
← Prev Question
Next Question →
Related questions
asked
Oct 14, 2017
175k
views
The time it takes to lay a sidewalk of a certain type varies directly as the length and inversely as the number of men working. If eight men take two days to lay 100 feet, how long will three men take
Bhordupur
asked
Oct 14, 2017
by
Bhordupur
8.1k
points
Mathematics
high-school
2
answers
0
votes
175k
views
asked
Sep 3, 2019
130k
views
the time it takes to lay a sidewalk of a certain type varies directly as the length and inversely as the # of men working. If eight men take 2 days to lay 100 ft, how long will it take 3 men to lay 150
Hans Sperker
asked
Sep 3, 2019
by
Hans Sperker
8.9k
points
Mathematics
college
1
answer
1
vote
130k
views
Ask a Question
Welcome to QAmmunity.org, where you can ask questions and receive answers from other members of our community.
9.5m
questions
12.2m
answers
Other Questions
How do you can you solve this problem 37 + y = 87; y =
How do you estimate of 4 5/8 X 1/3
A bathtub is being filled with water. After 3 minutes 4/5 of the tub is full. Assuming the rate is constant, how much longer will it take to fill the tub?
i have a field 60m long and 110 wide going to be paved i ordered 660000000cm cubed of cement how thick must the cement be to cover field
Write words to match the expression. 24- ( 6+3)
Twitter
WhatsApp
Facebook
Reddit
LinkedIn
Email
Link Copied!
Copy
Search QAmmunity.org