Two workers can paint a house in 7 hours. How much time will it take 3 workers to paint the same house?

1 Answer

3 votes

We have inverse proportion

Inverse proportion occurs when one value increases and the other decreases.

More workers on a job would reduce the time to complete the task. They are inversely proportional.

2w ----------------------- 7h

3w ----------------------- xh
___________________
(+) (-) ⇒ 2\3 = x\7 ⇒ x = 2·7/3=14/3 =12/3+2/3 =

= 4h + (2·60/3) min = 4h +40min